• Total Records: 223
NO. CASE NO. PARTIES ISSUES DATE OF JUDGMENT RESULT
1
BKI-12B-6/7-2015
Thien Lip Ha @ Annie AND OTHERS
Chiu Kwan Yiu
Appeal against decisions made after trial
15-12-2016
Decision of Court below set aside. Allow claim of RM119,000.00 plus 4% from date of 1.4.2011 till date of judgment &further 4% till date of payment. Cost of RM2,000.
2
BKI-24-78/8-2016
Bina Puri Construction Sdn Bhd
Syarikat Kapasi Sdn Bhd
-
15-12-2016
Allowed the claim as pr Encl. 1 with costs of RM20,000.00 Encl. 7 is disallowed. No costs. Set aside adjudication award. Allow the claim of Rm29,818,685.04.
3
BKI-22NCvC-16/2-2016
Tropical Pulpwood Resource Management Sdn. Bhd.
Sabah Forest Industries Sdn. Bhd.
NOTICE OF APPLICATION - (Order 14 of the Rules of Court 2012)
10-11-2016
Summary Judgment under Encl.17 is allowed with costs of RM7,500.
4
BKI-28NCC-52/9-2016
Hing Nyit Enterprise Sdn Bhd
Bina Puri Sdn Bhd
NOTICE OF APPLICATION - [Order 18 Rule 19(1) (b) & (d) and Order 92 Rule 4 of the Rules of Court 2012]
02-11-2016
In the circumstances, the striking out application of the winding up petition in BKI-28NCC-52/9-2016 is allowed with costs of RM15,000.00.
5
BKI-12A-10/7-2016
Rocktap Resources Sdn Bhd AND OTHERS
Ambank (m) Berhad
Appeal against interlocutory decision
27-10-2016
Affirmed ruling on 1st Appellant. Set aside ruling on 2nd and 3rd Appellants. Each parties to bear their own costs.
6
BKI-22NCvC-52/6-2014
Tristan Madison Lee Riven
Chua Keng Leong
-
25-10-2016
Plaintiff's claim and Defendant's counterclaim is dismissed with no order as to costs. The security for costs of RM30,000.00 to be returned.
7
BKI-22NCvC-68/8-2014
Tsai Ching Chi
Chang Ket Kiong @ William
Damages for repudiation of contract. Claim against defendants for joint and several liability of RM6,427,772.00 and other prayers.
18-10-2016
Judgment for the Plaintiff. Costs of RM25,000.00. Defendant's counterclaim is dismissed.
8
BKI-24C-2/3-2016
Asli Jati Engineering Sdn Bhd
Universiti Malaysia Sabah
Construction Industry Payment and Adjudication Act 2012
17-10-2016
Application dismissed with costs of RM6,500.00.
9
BKI-12B-6/4-2016
Telekom Malaysia Berhad
Globinaco Sdn. Bhd.
Appeal against decisions made after trial
06-10-2016
Appeal dismissed with costs of RM1,500.00.
10
BKI-41-17/11-2015
Johnny Matim
Public Prosecutor
SEK 323 KANUN KESEKSAAN RM2,000.00 jika gagal bayar penjara (3) bulan. Rayuan terhadap hukuman Majistret: Puan Dana Arabi Wazani Appeal against decisions made after trial
05-10-2016
Appeal dismissed. Affirmed findings of the Court below.